After assembling of biogas plant how can we ensure the the initiation of gas production?
Biogas-Plant Assembly-of-the-Biogas-plant 18-19 min 40-50 sec
Answers:
After 17 days of total curing time the raw material can be put into the Biogas plant.
Initial production of Biogas will take about 6 days. After that, it will be a regular daily production.
To check whether Biogas has been produced, do the following -
** Ensure that both the safety valves are in open position, for the gas to be conveyed.** Light the burner and check the flame for production of the Biogas.
Pls watch the Spoken Tutorial - Assembly of the Biogas plant.
https://spoken-tutorial.org/watch/Biogas+Plant/Assembly+of+the+Biogas+plant/English/
Answer to your question has been well explained with graphics.
After 17 days of total curing time the raw material can be put into the Biogas plant.
Initial production of Biogas will take about 6 days. After that, it will be a regular daily production.
To check whether Biogas has been produced, do the following -
** Ensure that both the safety valves are in open position, for the gas to be conveyed.** Light the burner and check the flame for production of the Biogas.
After 17 days of total curing time the raw material can be put into the Biogas plant.
Initial production of Biogas will take about 6 days. After that, it will be a regular daily production.