materials required to construct a biogas plant
Title
Question
how many days are required only for construction of plant?
How many labours are needed to complete this work?

Biogas-Plant Material-required-to-construct-a-Biogas-plant 07-08 min 40-50 sec 21-04-20, 10:58 p.m. biogasfdp

Answers:

Total number of days required to complete the civil work of a Biogas plantis 3 - 5 days.
One mason and three helpers are needed to complete this work.

Please watch the Spoken Tutorial Material required to construct a Biogas plant.

https://script.spoken-tutorial.org/index.php/Biogas-Plant/C3/Material-required-to-construct-a-Biogas-plant/English


For more information regarding the workers involved pls contact:
Dr. Prasad Deodhar
Bhagirath Rural Development Foundation

Village- Zarap, Taluka- Kudal,

Dist.- Sindhudurg


Spoken Tutorial series on Biogas Plant has been created under the guidance of Dr. Prasad Deodhar.

21-04-20, 11:21 p.m. bellatony911



Total number of days required to complete the civil work of a Biogas plantis 3 - 5 days.
One mason and three helpers are needed to complete this work.
21-11-23, 3:02 p.m. lingalapreethichikkidarathi


Total number of days required to complete the civil work of a Biogas plantis 3 - 5 days.
One mason and three helpers are needed to complete this work.
21-11-23, 3:05 p.m. Chikkisrivatsarichkidopreethi


Log-in to answer to this question.